Property Acquisition Status

The FM Area Diversion needs to acquire property rights that will be used for construction, temporary construction, or otherwise impacted by the project. Stay updated here with status reports from the MFDA.

Property Acquisition Schedule

Property Acquisition Status Reports

Find updates here as the process of property acquisition is carried out.

86.7%

Construction Footprint

36.7%

UMA Footprint

Property Acquisition Progress by Location

68.6%

Southern Embankment& Associated Infrastructure

36.7%

Upstream Mitigation Area

72%

Environmental Monitoring Easements

93.2%

Stormwater Diversion Channel

97.4%

Oxbow-Hickson-Bakke

100%

MFDA-Constructed In-Town Levees

100%

Drayton Dam Mitigation

119003538 118025206697466 778852663642806275 N

When & How Property Will Be Impacted

Get an overview of how certain land will be impacted by the comprehensive project, details on the schedule and acquisition process along with interactive maps and other land management resources.