97%

Construction Footprint

52.7%

UMA Footprint

Property Acquisition Progress by Location

91.1%

Southern Embankment& Associated Infrastructure

52.7%

Upstream Mitigation Area

75.5%

Environmental Monitoring Easements

100%

Stormwater Diversion Channel

100%

Oxbow-Hickson-Bakke

100%

MFDA-Constructed In-Town Levees

100%

Drayton Dam Mitigation