September 27, 2024
FM Area Diversion September Construction Update
FARGO, ND (September 27, 2024) – The Metro Flood Diversion Authority released its September construction update video for the FM Area Diversion project. In the past few weeks, roughly 2 million cubic yards of material have been excavated. For perspective, that is enough to cover the entire North Dakota State University campus to a depth of nearly 5 feet. Thousands of cubic yards of concrete also were placed across several locations. Here is a closer look at this month’s highlights.
This progress and other updates can be viewed at the September 2024 Construction Flyover video.
Transcript: September 2024 MFDA Construction Flyover
Click to expand transcript
Tom Fuchs (Senior Construction Manager): [00:00:01] Hi, I’m Tom Fuchs, the senior construction manager for the Metro Flood Diversion Authority with this month’s project update.
[00:00:10] ASN Constructors teams have continued to dig down to excavate the stormwater diversion channel while building up to construct the bridges that will cross over it. In reach 10, which is just south of I-94, crews are placing excavated material for the non-embedded levee which must be constructed in warmer weather. Levee construction is also the focus in reaches 11 and 12.
[00:00:57] Further south in reach 13 of the channel, south and west of Horace, North Dakota, crews are digging the main channel and placing the excavated material in berms on both sides. Close to another 2 million cubic yards of the necessary 45 million were moved in the past month, bringing channel excavation to about 57% completion.
[00:01:28] Work also continues on many of the 19 channel crossings. At County Road 20, ASN Constructors started early to pour approximately 700 cubic yards of concrete needed for the bridge deck. North of there at the County Road 22 crossing, bridge girders are now installed.
[00:02:24] Northeast of Argusville, North Dakota, near the diversion outlet, ASN Constructors is working toward completion of the combined County Road 4 and 31 crossing. Crews have now backfilled both abutments including installing geofoam, a lightweight fill material that mitigates settlement, and they are beginning to construct the concrete approach slabs.
[00:03:11] West of the metro area on I-94, bypass lanes are now fully constructed and will be ready to open before winter. ASN has completed mainline pavement removal and constructed portions of the required grade raises for the new crossings.
[00:03:46] Over at the Maple River Aqueduct, where the river rather than cars will cross over the channel, ASN has continued constructing segments of the concrete flume base and has begun form work and concrete placement for the first portion of the north flume wall.
[00:04:28] At the Red River Structure, Ames Construction is nearing completion of concrete work for the control structure. The US Army Corps of Engineers contractor also began driving sheet piles and H-piles as well as placing concrete at the flood walls east and west of the structure. Crews also began excavating and stockpiling roughly 460,000 cubic yards of impervious fill east of the Red River on the Minnesota side of the project. This material, which is enough to fill the US Capitol Dome more than nine times, will be used to construct the embankment that will cross the Red River after the river is permanently diverted through the structure in 2025.
[00:05:24] A Corps contractor has also been working on the Oxbow-Hickson-Bakke ring levee. Hendrickson Transportation has completed more than a mile of the inspection trench. They’ve also completed about 3,000 of the 11,500-foot-long embankment using excavated material from the north borrow pond.
Channel Crossings: ASN Constructors continued work on many of the 19 road and railroad bridges that will cross the stormwater diversion channel. The bypass lanes on I-94 are now fully constructed and will open before winter. Bridge girders were installed at the County Road 22 crossing, and some of the final portions of the combined County Roads 4 and 31 crossing were completed, putting it on track to open to traffic before winter, as well. Additionally, about 700 cubic yards of concrete was poured for the County Road 20 bridge deck this month.

Maple River Aqueduct: Concrete placement continues on this one-of-a-kind structure, where about 9,500 cubic yards of concrete have been placed to date.
Oxbow-Hickson-Bakke Ring Levee: Hendrickson Transportation, a U.S. Army Corps of Engineers contractor, completed more than a mile of the inspection trench as well as about 3,000 feet of the 11,500-foot-long-embankment.
Red River Structure: Ames Construction, a U.S. Army Corps of Engineers contractor, neared the end of the concrete work on the control structure portion this month, and they began excavating and stockpiling roughly 460,000 cubic yards of fill on the Minnesota side of the river. This material, which is enough to fill the U.S. Capitol Dome more than nine times, will be used to construct the embankment that will cross the Red River after the river is permanently diverted through the structure in 2025.

Stormwater Diversion Channel: Mass excavation took place in Reaches 10, 11,12, and 13 of the channel, which extend from just south of I-94 to south of Horace, North Dakota. Close to another 2 million cubic yards of the necessary 45 million were moved in the past month, bringing channel excavation to about 57% completion.
For the latest road closures and more construction information, go to FMDiversion.gov.
About the Metro Flood Diversion Authority
The MFDA is a permanent North Dakota political subdivision that is cooperatively implementing the Fargo-Moorhead Area Diversion comprehensive project with the U.S. Army Corps of Engineers. The MFDA works in partnership with the Red River Valley Alliance in a public-private partnership as well as the City of Fargo, City of Moorhead, Cass County, Clay County and the Cass County Joint Water Resource District.
For current photos of FM Area Diversion project construction, please contact Amy Wieser Willson at amy@neonloon.com or 218-535-5359.