November 22, 2026
FM Area Diversion November Construction Update
FARGO, N.D. (November 20, 2026) – Contractors completed another stretch of the FM Area Diversion’s 22-mile southern embankment this month and made progress on numerous other components.
At Reach SE-2B, the U.S. Army Corps of Engineers contractor wrapped up work on the four-mile stretch of the embankment that will hold back floodwater when the FM Area Diversion operates. In addition to the levee, crews raised both 45th Street and County Road 16 along with existing public service utilities, including Cass Rural Water and Cass County Electric. These all now pass up and over the embankment to maintain transportation and utility connectivity. Contractors also installed systems of ditches, culverts and drop structures to intercept, collect and convey stormwater runoff even when the project does not operate.

After working on repairs to the Highway 81 crossing over Reach SE-3 of the southern embankment, contractors closed in on completing the work necessary to reopen the road for winter. As part of this work, contractors lengthened the box culvert passing under Highway 81 and flattened the roadway embankment slopes on both sides. Crews placed gravel surfacing as well as topsoil and turf reinforcement matting along the completed slopes of the roadway embankment. Final paving can be expected in the spring.
At the Maple River Aqueduct this month, ASN Constructors completed excavation for the spillway approach channel where excess river flows will be diverted into the stormwater diversion channel when needed. ASN also installed supports and instrumentation for measuring flow and water levels.
Just upstream, crews worked on excavating and reshaping the riverbank on the aqueduct’s approach to a benched configuration to accommodate the necessary flow ranges while maintaining suitable flow velocities in the Maple River. Benched portions of the riverbank received toe wood-sod mat restoration, where crews installed harvested trees to underpin and shore the bank slopes below the benches. They used a mixture of woody debris and soil along with sod mats and live cuttings to create the benches, which will provide streambank protection and promote natural stability and habitat.
Work also continued on mitigation projects, including installing a ring levee around Cass Rural Water’s Reservoir A and its associated well field and water treatment facilities. The contractor wrapped up the one mile of embankment construction and began applying topsoil and turf reinforcement matting this month. They also continued installing the last remaining water line connections to the new wells.
Watch these updates and more in the new drone construction update at https://youtu.be/ExUuao8JDYQ.
About the Metro Flood Diversion Authority
The MFDA is a permanent North Dakota political subdivision that is cooperatively implementing the Fargo-Moorhead Area Diversion comprehensive project with the U.S. Army Corps of Engineers. The MFDA works in partnership with the Red River Valley Alliance in a public-private partnership as well as the City of Fargo, City of Moorhead, Cass County, Clay County and the Cass County Joint Water Resource District.