June 29, 2024

FM Area Diversion June Construction Update

FARGO, ND (June 29, 2024) – The Metro Flood Diversion Authority has released the June construction update for the FM Area Diversion project.

This progress and other updates can be viewed at the June 2024 Construction Flyover video.

Transcript: June 2024 Construction Flyover

Click to expand transcript

Tom Fuchs: [00:00:00] More than two dozen FM Area Diversion project sites are under construction right now. I’m Tom Fuchs, senior construction manager for the Metro Flood Diversion Authority, with some of those construction highlights.

[00:00:09] ASN Constructors has now started portions of work at all of the 19 road and railroad crossings that will span the stormwater diversion channel. This month, pre-cast concrete girders are being installed at the County Road 20 crossing north and west of the FM Metro. More than 500 girders will be necessary to complete all bridges and crossings constructed as part of the stormwater diversion channel.

[00:00:43] Travelers on I-94 west of the metro area have noticed ramp and lane closures recently as ASN constructs bypasses. These were paved this month and traffic is now routed on the bypasses. Work continues in the area as the remaining lanes will be tied in and mainline reconstruction commences.

[00:00:58] North and west of Harwood, North Dakota, trains have also begun running on the completed bypass, called a shoefly. After the existing ballast and track are removed, ASN will begin to excavate and drive piles for the new crossing at the site. Nearby at I-29, where traffic was bypassed last year, we can see bridge substructure work now well underway for the new crossings in both the north and southbound directions.

[00:01:32] Work can also be observed on reach 13 of the stormwater diversion channel. It is one of nine reaches currently under construction for the 30-mile channel. The many rainy days in recent weeks slowed excavation of the clay soil, but ASN still moved about 400,000 cubic yards of material in the past month, bringing them close to 21 million cubic yards that have been excavated so far.

[00:01:54] Things are taking shape at the Maple River Aqueduct as well. ASN is continuing to place concrete for the pier and abutment walls and the adjacent wing wall footings. We can also see falsework, a temporary structure, in place for the first segments of the aqueduct flume. Once completed, the Maple River will flow across the aqueduct flume as the diversion channel flows in the conduits below it.

[00:02:26] As we move south of the metro area, we can see work being done by the US Army Corps of Engineers on the 22-mile southern embankment. Work recently began on reach SE 2B, which lies near the Wild Rice River Structure. R.J. Zavoral and Sons, the Corps of Engineers contractor there, is beginning to strip topsoil, excavate, and backfill the inspection trench. It is also preparing to construct the initial portions of the embankment spanning from County Road 16 south to the tie-in to the Wild Rice River Structure.

[00:03:06] Earthwork also is just beginning on a ring levee that will protect the Oxbow-Hickson-Bakke community. Close to 1.5 million cubic yards will be excavated and placed to construct the remaining 2 miles of ring levee system north and west of County Road 81. Those are highlights of just some of the many components under construction this summer.

Work is taking place on more than two dozen components. Here are some highlights.

Mfda I 94 2
ASN Constructors paved bypass lanes on I-94 west of the Fargo-Moorhead metro area in preparation of building a crossing for the stormwater diversion channel there.

Channel Crossings: ASN Constructors has begun work on all 19 road and railroad crossings that will span the stormwater diversion channel. More than 500 bridge girders will be used to complete all the work.

Mfda Mras 1
Construction continues on the Maple River Aqueduct, which will route the Maple River over the top of the stormwater diversion channel.

Maple River Aqueduct: ASN Constructors continued to place concrete for the pier and abutment walls and the adjacent wingwall footings this month. They also have placed a temporary structure that will allow work to begin on the aqueduct flume.

OHB Ring Levee: Excavation work began this month on a ring levee that will protect the Oxbow-Hickson-Bakke community. The contractor will construct the last remaining portions of the ring levee system north and west of County Road 81.

Red River Structure: Assembly continues on the first of three 50-foot-wide radial arm gates on the structure, which is now 57% complete. Ames Construction also is placing concrete and fabricating the second and third gates.

Southern Embankment: Work recently began on reach SE-2B, which lies near the Wild Rice River Structure. R.J. Zavoral & Sons, the U.S. Army Corps of Engineers contractor there, began to strip topsoil, build an inspection trench, excavate material, and construct a portion of the 22-mile embankment.

Reach 13
ASN Constructors excavates material in Reach 13 of the 30-mile stormwater diversion channel.

Stormwater Diversion Channel: Wet weather slowed excavation this month, but ASN Constructors still moved about 400,000 cubic yards of material in nine separate reaches. To date, roughly 21 million cubic yards have been excavated.

Wild Rice River Structure: Ames Construction, a Corps of Engineers contractor, put finishing touches on the structure, including adding railings and ladders and painting.

About the Metro Flood Diversion Authority

The MFDA is a permanent North Dakota political subdivision that is cooperatively implementing the Fargo-Moorhead Area Diversion comprehensive project with the U.S. Army Corps of Engineers. The MFDA works in partnership with the Red River Valley Alliance in a public-private partnership as well as the City of Fargo, City of Moorhead, Cass County, Clay County and the Cass County Joint Water Resource District. More information is available at www.FMDiversion.gov.

Media Contact: Amy Wieser Willson