MFDA Board Meeting – July 24, 2025
3:30 pm - 5:00 pm
1. Call to Order
- a. Roll Call of Members
2. Approve minutes from June 26, 2025
[Attachment 01.00] (Pg. 3)
3. Approve minutes from July 2, 2025, Special Meeting
[Attachment 02.00] (Pg. 8)
4. Approve Order of Agenda
5. CONSENT AGENDA – APPROVE THE FOLLOWING:
- a. Finance Report [Attachment 03.00] (Pg. 10)
- b. Voucher Approval [Attachment 04.00] (Pg. 34)
- c. Budget Change Requests
- i. BCR 020 – Minnkota Task Order 8 [Attachment 05.01] (Pg. 51)
- d. DA Board Approval Contracting Actions [Attachment 06.00] (Pg. 52)
- i. Minnkota Task Order 8, Amendment 0 [Attachment 06.01] (Pg. 54)
- ii. WP 52H – Raymond Township Mobility Improvement Award
[Attachment 06.02] (Pg. 56)
- e. Sale of Excess Land Recommendations
- i. OINs 2366, 2367 & 8852 Sale of Excess Land [Attachment 07.01] (Pg. 59)
- ii. OIN 7004 Sale of Excess Land [Attachment 07.02] (Pg. 71)
- iii. OIN 9347 Sale of Excess Land [Attachment 07.03] (Pg. 81)
- iv. OIN 1834 Sale of Excess Land [Attachment 07.04] (Pg. 89)
- v. OIN 7249 Sale of Excess Land Recommendation [Attachment 07.05] (Pg. 97)
REGULAR AGENDA:
6. Executive Director Update
- a. MFDA Mid-Year Review
7. General Counsel Update
- a. Dispute Resolution Board Update
- b. Settlement Agreement Implementation Update
8. Project Updates
- a. USACE Project Update [Attachment 08.00] (Pg. 102)
- b. SWDCAI Project Update [Attachment 09.00] (Pg. 104)
- c. Project Safety Update [Attachment 10.00] (Pg. 105)
- d. P3 Monthly Update [Attachment 11.00] (Pg. 106)
- e. Monthly Drone Footage Video
9. Communications Team Update
10. Land Management Update
- a. Property Acquisition Status Report [Attachment 12.00] (Pg. 143)
11. Finance Update
- a. BCR 021 – P3 Developer Statement of Principles 2025 Payments
[Attachment 13.00] (Pg. 150) - b. Sales Tax Collections Update
[Attachment 14.00] (Pg. 151)
12. Other Business
13. Public Comment – 15 minutes maximum. Each speaker is limited to three minutes.
14. Next Meeting: August 28, 2025
15. Adjournment
Files
SEE FULL PACKETAttend This Meeting
Fargo City Hall Commission Chambers225 4th St. North
Fargo, ND 58102 Get Directions
Live Viewing Options
Turn your TV channel to Fargo 56 Live
Stream the meeting on The City of Fargo Youtube Channel.
701-296-6904 access code 4378
A regular meeting of the Metro Flood Diversion Authority Board of Authority was held on July 24, 2025. The following members were present: Bernie Dardis, Mayor, City of West Fargo; Dr. Tim Mahoney, Mayor, City of Fargo; Chuck Hendrickson, Moorhead City Council; David Ebinger, Clay County Commissioner; Tony Grindberg, Cass County Commissioner; Rick Steen, Cass County Joint Water Resource District; Dave Piepkorn, Fargo City Commissioner; Kevin Campbell, Clay County Commissioner; Jim Kapitan, Cass County Commissioner; Lisa Borgen, Moorhead City Council and Denise Kolpack, Fargo City Commissioner.
Member(s) absent: Shelly Carlson, Mayor, City of Moorhead and Duane Breitling, Cass County Commissioner.
1. CALL TO ORDER
Mr. Grindberg called the meeting to order at 3:31 PM. Roll call was taken, and a quorum was present.
2. APPROVE THE MINUTES FROM THE JUNE 26, 2025, MEETING
MOTION PASSED
Ms. Kolpack moved to approve the minutes from the June 26, 2025, meeting and Ms. Borgen seconded the motion. On a voice vote, the motion carried.
3. APPROVE THE MINUTES FROM THE JULY 2, 2025, SPECIAL MEETING
MOTION PASSED
Mr. Ebinger moved to approve the minutes from the July 2, 2025, special meeting and Mr. Kapitan seconded the motion. On a voice vote, the motion carried.
4. APPROVE THE ORDER OF THE AGENDA
MOTION PASSED
Mayor Mahoney moved to approve the order of the agenda as presented and Mr. Kapitan seconded the motion. On a voice vote, the motion carried.
5. APPROVE THE CONSENT AGENDA
MOTION PASSED
Mr. Piepkorn moved to approve the consent agenda, amending item 5., e., v., to state sale as recommended by the Land Management Committee and Mr. Kapitan seconded the motion. On a roll call vote, the motion carried
6. EXECUTIVE DIRECTOR UPDATE
MFDA Mid-Year Review
Mr. Benson presented the 2025 mid-year review, highlighting the successes. The presentation can be viewed in its entirety on www.fmdiversion.gov.
7. GENERAL COUNSEL UPDATE
a. Technical Dispute Review Board Update
Mr. Shockley reported that the TDRB held a virtual organizational meeting on July 15, 2025; they will continue to hold meetings every quarter with two on-site meetings at the MFDA office, annually. All the pending disputes were resolved and withdrawn per the settlement agreement.
8. PROJECT UPDATES
USACE Project Update
Mr. Grindberg introduced Colonel Matthew Chase, the new USACE St. Paul District Commander. Colonel Chase shared his background and stated that he is looking forward to leading the St. Paul District.
Ms. Williams provided the following USACE update:
1 Diversion Inlet Structure (DIS) – Construction
Structure includes 3-50 ft. wide Tainter gates. Construction is 99% complete. Completion date is now 28 Oct 2025. Training held 19 June. Final inspections upcoming. Turnover to Sponsors for OMRRR anticipated in November 2025.
2 Wild Rice River Structure (WRRS) – Construction
Structure includes 2-40 ft. wide Tainter gates. Construction is 98% complete. Completion date is now 28 November 2025. Operating machinery corrections, final inspections and training upcoming. Turnover to Sponsors for OMRRR anticipated in December 2025.
3 Red River Structure (RRS) – Construction
Structure includes 3-50 ft. wide Tainter gates. Construction is 81% complete. Construction completion date is 30 April 2026. East and west dam wall and approach apron and gate machinery install ongoing. Red River re-route rescheduled for 7 Aug 2025 due to wet and high river conditions.
4 Southern Embankment – Reach SE-2A – Construction
Construction is 76% complete but continues to be behind schedule. Scheduled completion date of 13 October 2024 was not met. Revised schedule and completion date pending.
5 Drain 27 Wetland Mitigation Project Plantings – Construction
Native plantings 5-year contract for wetland establishment. Completion date is 1 December 2027. Contractor replanting areas disturbed by adjacent producers.
6 FY2024 Contract Awards – Construction
OHB Ring Levee: 50% complete. Levee construction ongoing. Contractor digging inspection trench. Contract completion date is 17 October 2025. Reach SE-1B: 36% complete. Anticipate opening CR16/17 by October 2025. Contract completion date is 13 March 2026. Reach SE-2B: 45% complete. Embankment construction ongoing. Paving of CR16 crossing pending. Contract completion date is 23 August 2026. Forest Mitigation #1: Contractor is planting. Contract completion date is 31 Dec 2028. Reach SE-4: 9% complete. Embankment construction continues. road work. Contract completion date is 30 September 2026.
7 FY2025 Contract Awards – Construction
SE-3: 2% complete. Embankment construction continues. Contract completion date is 11 September 2026. SE-5: Contractor is clearing and grubbing. Wolverton Creek crossing must be complete by 15 Nov 2025. Contract completion date is 8 September 2026. Forest Mitigation #2: Contractor is planting. Contract completion date is 31 Dec 2029.
8 I-29 Raise – Operations and Maintenance (OMRRR)
Turnover to MFDA occurred on 20 December and preparation of O&M documents is ongoing.
9 Drayton Dam Mitigation Project Design – Operations and Maintenance (OMRRR)
Turnover to MFDA for O&M occurred on 28 Nov 2023. OMRRR manual coordination continues.
b. SWDCAI Project Update
Mr. Bakkegard provided an update of the construction map that shows current work in progress, 30- and 60-day projected progress:
30- to 60-Day Outlook
CR-10, I-29, CR-22, BNSF Hillsboro
BNSF Prosper
I-94
Drain 21C Inlet
SE-2B
Red River Structure
Misc. Highlights
Channel Excavation
Rush River Inlet
Authority Administration Building
c. Project Safety Update
Mr. Bakkegard provided the safety update for the period June 1 to June 30, 2025. He reported that there were two minor incidents that included heat exhaustion and a fractured finger requiring first aid but overall, it was a good month and there were no other incidents to report.
d. P3 Monthly Update
Mr. Bakkegard highlighted the road closure section in the July P3 monthly update.
TEMPORARY ROAD CLOSURES AND ANTICIPATED MAINLINE OPENING DATE
Interstate 29 – Bypass Operational August 2025
County Road 81 – Bypass Operational August 2025
County Road 22 – Bypass Operational July 2025
County Road 20 – Crossing Open to the public June 2025
County Road 10 – Bypass Operational June 2025
32nd Ave – Traffic Detoured to CR 8 and CR 31 August 2025
52nd Ave – Traffic Detoured to CR 8 and CR 31 August 2025
Interstate 94 – Bypass Operational August 2025
Interstate 94 – Eastbound Left Lane Closure
County Road 6 – Bypass Operational September 2025
ROADWAYS CURRENTLY CLOSED
24th St SE – Closed 9/21/2022
172nd Ave. SE – Closed 9/19/2022
171st Ave. SE – Closed 10/31/2023
170th Ave. SE – Closed 10/31/2023
169th Ave. SE – Closed 6/21/2023
29th St. SE – Closed 9/17/2023
32nd St. SE – Closed 3/20/2024
37th St. SE – Closed 9/20/2023
166th Ave. SE – Closed 5/24/2024
43rd St. SE – Closed 10/7/2024
38th St. NW – Closed 10/7/2024
112th Ave. S – Closed 10/10/2024
64th Ave. S – Closed 10/7/2024
45th St. SE – Closed 10/10/2024
26th St. W – Closed 10/15/2024
21st Ave. W – Closed 10/15/2024
21st Ave. W – Closed 10/15/2024
35th St. SE – Closed 10/7/2027
UPCOMING PERMANENT ROAD CLOSURES (TENTATIVE SCHEDULE)
32nd Ave. NW – Planned date August 2026 (MRA Access)
40th Ave. / CR 8 – Planned date August 2025
81st S – Planned date August 2026 (SRA Access)
ACTIVE BYPASSES
CR 81, I-29, CR 22, CR10, I-94 and CR6
ACTIVE BRIDGES
CR 4/31 and CR32 Crossing
ACTIVE DETOURS
32nd/52nd Ave. W Crossings
UPCOMING DETOURS
38th St. West and CR 16/17
Please reach out to Mr. Barthel if you have any questions regarding the report.
e. Monthly Drone Video
A video highlighting the progress that has been achieved since June 2025 was viewed.
9. COMMUNICATIONS TEAM UPDATE
Ms. Wieser Willson provided the following communications update:
Outreach Products
Media Relations:
June construction update
Settlement agreement
New lands director
Newsletter:
Faces of the Diversion: Tim King
The Diversion Current: Red River Structure
Outreach:
Lions Club presentation
10. LAND MANAGEMENT UPDATE
Property Acquisition Status Report
Mr. Fisher provided the following property acquisition status report:
98.4% completion in the Construction Footprint
61.3% completion in the UMA Footprint
95.3% of the parcels in the Southern Embankment have been acquired
61.3% of the parcels in the Upstream Mitigation Area have been acquired
78.1% of the Environmental Easements have been signed
100.0% completed: Stormwater Diversion Channel; Oxbow-Hickson-Bakke levee; in-town levees and the Drayton Dam mitigation
Key Activities:
Continued negotiating settlement agreements for existing eminent domain actions
In the last month, successfully closed on 1 parcel / 1 owners in the UMA
Continuing the process of disposing of Excess Lands
43 parcels / 739.92 acres have been approved as Excess Lands
11 parcels / 344.20 acres are moving through the Policy
32 parcels / 395.72 acres have been sold or pending closing
Continuing efforts to dispose of the abandoned rail corridor in Horace, ND
Auction of 6 Excess Land parcels on July 22
Completed plats of Diversion Channel lands in 5 of the 7 townships, working to finalize plats for the remaining 2 townships
Preparing for eminent domain trials starting in August 2025.
11. FINANCE UPDATE
Mayor Dardis reported that the finance committee met and approved the bills payable through July 15, 2025, in the amount of $4,594,797. A Budget Change Request of $20,000,000, was approved that will bring the current 2025 cash budget to $4,447,555,689.
a. BCR 021 – Developer Statement of Principles 2025 Payments
Mr. Barthel provided an overview and summary of the above-referenced Budget Change Request:
Obligate $20 million of the P3 program contingency to the 2025 cash budget to support Section 22 of the Statement of Principles (SOP) executed 7/3/2025. The 2025 cash budget will increase from $427,555,689 to $447,555,689 as a result of this change and includes BCR-020 Minnkota Power substation relocation. Request justification: the Statement of Principles (SOP) executed on July 3, 2025, resolves various commercial issues and, as such payments to the Developer in 2025 are to be made according to Section 22 of the SOP.
MOTION PASSED
Ms. Kolpack moved to approve the Budget Change Request as presented and Mayor Mahoney seconded the motion. On a roll call vote, the motion carried.
b. Sales Tax Update 2024 Collections
There was no sales tax update.
12. OTHER BUSINESS
There was no other business to discuss.
13. PUBLIC COMMENT
There were no public comments.
14. NEXT MEETING
The next meeting will be on August 28, 2025.
15. ADJOURNMENT
The meeting adjourned at 4:11 PM.