FM Area Diversion Board Meeting – December 19, 2024
3:30 pm - 5:00 pm
1. Call to Order
a. Roll Call of Members
2. Approve minutes from November 21, 2024
[Attachment 00.01] (Pg. 3)
3. Approve Order of Agenda
4. CONSENT AGENDA – APPROVE THE FOLLOWING:
a. Finance Report [Attachment 01.00] (Pg. 7)
b. Voucher Approval [Attachment 02.00] (Pg. 39)
c. MOUs and Agreements [Attachment 03.00] (Pg. 58)
i. Montana Dakota Utilities & MFDA Extension Agreement (Under add’l staff review)
[Attachment 03.01] (Pg. 60)
d. DA Board Approval Contracting Actions [Attachment 04.00] (Pg. 69)
i. WP 38C Task Order 34 for OINs 856 – 1972 [Attachment 04.01] (Pg. 72)
ii. Neon Loon MSA, Amendment 1 [Attachment 04.02] (Pg. 75)
iii. Flint Communications Service Agreement Amendment 3 [Attachment 04.03] (Pg. 77)
iv. GA Group Service Agreement Amendment 4 [Attachment 04.04] (Pg. 80)
v. TF Powers WP 38C New Master Agreement for Construction Services [Attachment 04.05] (Pg. 83)
vi. Park Construction WP 38C Master Agreement for Construction Services [Attachment 04.06] (Pg. 85)
vii. PWS, Inc. WP 38C Master Agreement for Construction Services [Attachment 04.07] (Pg. 87)
viii. Linn Co. WP 38C Master Agreement for Construction Services [Attachment 04.08] (Pg. 89)
e. Resolution Amending the Appointment of Members to the Diversion Authority Board, the Land Management Committee, and the Finance Committee of the MFDA [Attachment 05.00] (Pg. 91)
REGULAR AGENDA:
5. Co-Executive Director Update
a. MFDA Award Solicitation/Procurement Policy
[Attachment 06.00] (Pg. 95)
b. MFDA Sponsorship Policy
[Attachment 07.00] (Pg. 101)
6. General Counsel Update
7. Project Updates
a. USACE Project Update [Attachment 08.00] (Pg. 107)
b. SWDCAI Project Update [Attachment 09.00] (Pg. 109)
c. Project Safety Update [Attachment 10.00] (Pg. 110)
d. P3 Monthly Update [Attachment 11.00] (Pg. 111)
e. 2024 Year in Review Project Video
8. Communications Team Update
9. Land Management Update
a. Property Acquisition Status Report [Attachment 12.00] (Pg. 142)
b. Finance Update
10. Other Business
a. 2025 MFDA Contract Rates [Attachment 13.00] (Pg. 149)
11. Next Meeting: January 23, 2025
12. Adjournment
Files
SEE FULL PACKETAttend This Meeting
Fargo City Hall Commission Chambers225 4th St. North
Fargo, ND 58102 Get Directions
Live Viewing Options
Turn your TV channel to Fargo 56 Live
Stream the meeting on The City of Fargo Youtube Channel.
701-296-6904 access code 4378
A regular meeting of the Metro Flood Diversion Authority Board of Authority was held on December 19, 2024.
The following members were present: Bernie Dardis, Mayor, City of West Fargo; Dr. Tim Mahoney, Mayor, City of Fargo; Chuck Hendrickson, Moorhead City Council; David Ebinger, Clay County Commissioner; Kevin Campbell, Clay County Commissioner; Duane Breitling, Cass County Commissioner; Tony Grindberg, Cass County Commissioner; Larry Seljevold, Moorhead City Council; Rick Steen, Cass County Joint Water Resource District; Dave Piepkorn, Fargo City Commissioner; Shelly Carlson, Mayor, City of Moorhead and Denise Kolpack, Fargo City Commissioner.
Member(s) absent: Jim Kapitan, Cass County Commissioner.
1. CALL TO ORDER
Mayor Carlson called the meeting to order at 3:30 PM. Roll call was taken, and a quorum was present.
2. APPROVE THE MINUTES FROM THE NOVEMBER 2024 MEETING
MOTION PASSED
Ms. Kolpack moved to approve the minutes from the November 2024 meeting and Mr. Ebinger
seconded the motion. On a voice vote, the motion carried.
3. APPROVE THE ORDER OF THE AGENDA
MOTION PASSED
Mayor Dardis moved to amend the order of the agenda, removing item 4.c., i., from the Consent Agenda. Mr. Hendrickson seconded the motion and on a voice vote, the motion carried.
4. APPROVE THE CONSENT AGENDA
MOTION PASSED
Mayor Mahoney moved to approve the Consent Agenda as amended and Ms. Kolpack seconded the motion. On a roll call vote, the motion carried.
5. CO-EXECUTIVE DIRECTOR’S UPDATE
a. MFDA Award Solicitation/Procurement Policy
Mr. Wilson provided an overview and summary of the Award Solicitation Policy and asked the Board for approval of the policy.
MOTION PASSED
Mr. Seljevold moved to approve the policy as presented and Mr. Ebinger seconded the motion. On a roll call vote, the motion carried.
b. MFDA Sponsorship Policy
Mr. Wilson provided an overview and summary of the Sponsorship Policy and asked the Board for approval of the policy.
MOTION PASSED
Mayor Mahoney moved to approve the policy as presented and Ms. Kolpack seconded the motion. On a roll call vote, the motion carried.
6. GENERAL COUNSEL UPDATE
Mr. Shockley did not have an update.
7. PROJECT UPDATES
a. USACE Project Update
Ms. Williams provided the following USACE update:
1 Diversion Inlet Structure (DIS) – Construction: Structure includes 3-50 ft. wide Tainter gates. Construction is 99% complete. Construction completion date will be revised pending outcome of modifications to the gate machinery design. Schedule for remaining work: 2024-2025: Complete operating machinery corrections; training and commissioning.
2 Wild Rice River Structure (WRRS) – Construction: Structure includes 2-40 ft. wide Tainter gates. Construction is 98% complete. Construction completion date will be revised pending outcome of modifications to the gate machinery design. Schedule for remaining work: 2024-2025: Complete operating machinery corrections; training and commissioning.
3 I-29 Raise – Construction: Includes approximately 4 miles of interstate raise between County Roads 16 and 18. Construction is 100% complete. Final inspection held 3 January 2024; turf establishment inspection held 29 August. Preparation of O&M documents and turnover is ongoing.
4 Red River Structure (RRS) – Construction: Structure includes 3-50 ft. wide Tainter gates. Construction is 70% complete. Construction completion date is 19 March 2026. Tainter gate #2 continues to be assembled on site and delivery of gate #3 and mechanical equipment is ongoing.
5 Drain 27 Wetland Mitigation Project Plantings – Construction: Native plantings 5-year contract awarded 17 May 2023. Completion date for wetland establishment is 1 December 2027. Encroachments continue to be an issue.
6 Drayton Dam Mitigation Project Design – Construction
Construction is complete. Turnover to MFDA for O&M occurred on 28 Nov 2023. OMRRR manual will be finalized once MFDA provides comments.
7 Southern Embankment – Reach SE-2A – Construction: Construction is 75% complete but continues to be behind schedule. Scheduled completion date of 13 October 2024 was not met. Revised schedule and completion date pending.
8 FY2024 Contract Awards:
OHB Ring Levee: Awarded 22 February and is 12% complete. Inspection trench, earthwork and storm sewer activities ongoing. Contract completion date is 31 August 2025.
Reach SE-1B: Awarded 27 February and is 29% complete. Stripping, hauling, road subgrade and box culvert work continues. Contract completion date is 13 March 2026.
Reach SE-2B: Awarded 11 March and is 37% complete. CR 16 to be opened for winter. Contract completion date is 30 October 2025.
Forest Mitigation #1: Contractor is preparing lands for additional planting next season. Reach SE-4: 130th realignment and north embankment work ongoing. Contract completion date is 3 June 2026.
9 FY25 Contract Awards:
SE-3: Bid opening held 26 November. HSG Park JV 2, LLC is the low bidder. Contract award: January 2025.
SE-5: Bid opening scheduled for 13 December. Contract award: January 2025.
Forest Mitigation #2: Advertise 16 December 2024. Award in February 2025.
b. SWDCAI Project Update
Mr. Bakkegard provided an update of the construction map that shows current work in progress, 30- and 60-day projected progress:
30- to 60-Day Outlook
• CR-32 Crossing
• Maple River Aqueduct
• Red River Structure
Misc. Highlights
• Channel Reaches 1 & 2
• BNSF Prosper
• Sheyenne Aqueduct
• Channel Excavation
• SE-2B
c. Project Safety Update
Mr. Bakkegard provided the safety update for the period November 1, 2024, to November 30, 2024. He reported that an individual was electrocuted and has suffered severe injuries. Another employee partially lost a finger in an incident with a drill. There were no other incidents to report.
d. P3 Monthly Update
Mr. Barthel provided a brief summary indicating that the commercial matters team are working with ASN and RRVA to ensure that everything gets paid and any changes get properly documented. The MFDA has initiated 23 change requests to date. Please reach out to Mr. Barthel if you have any questions regarding the report.
e. 2024 Year in Review Project Video
A video highlighting 2024 and the progress that has been achieved was viewed.
8. COMMUNICATIONS TEAM UPDATE
Ms. Willson provided the following communications update:
Outreach Products
Media Relations:
• November construction update release
• Year-in-review release with video and infographic
Event Facilitation:
• Rotary Club project update
9. LAND MANAGEMENT UPDATE
a. Property Acquisition Status Report
Mr. Dodds provided the following property acquisition status report:
• 98.4% completion in the Construction Footprint
• 57.5% completion in the UMA Footprint
• 95.3% of the parcels in the Southern Embankment have been acquired
• 57.5% of the parcels in the Upstream Mitigation Area have been acquired
• 77.3% of the Environmental Easements have been signed
• 100.0% completed: Stormwater Diversion Channel; Oxbow-Hickson-Bakke levee; in-town levees and the Drayton Dam mitigation
Key Activities:
• Continued negotiating settlement agreements for existing eminent domain actions
• In the last month, successfully closed on 21 parcels / 5 owners in the UMA and Southern Embankment
• Completing appraisal reports for Christine area flowage easements and Sheyenne River Benching Project
• Continuing the process of disposing of Excess Lands
• 39 parcels / 682.83 acres have been approved as Excess Lands
• 17 parcels / 546.36 acres are moving through the Policy
• 22 parcels / 136.47 acres have been sold or pending closing
• Continued work on farmland leases for 2025
• Reminder: The vacate dates for occupied Minnesota properties
• Deadline in Clay County = April 1st, 2025
• Deadline in Wilkin County = June 1st, 2025
11. FINANCE UPDATE
Mayor Dardis reported that the December bills payable total $7,060,087, and the current grand total net position is $283,095,804. Mayor Dardis also reported that version 3 of the draft 2025 cash budget was presented, and the final 2025 cash budget will be presented at the January meeting. The current proposed cash budget is $421,172,019.
12. OTHER BUSINESS
a. MFDA 2023 & 2024 Rates Summary
Mr. Barthel reported that the contract summary has been reviewed and noted that there hasn’t been much consistency in the rate increases over the last five years. Mr. Barthel asked the committee members to review the report and to reach out to him with any questions.
13. NEXT MEETING
The next meeting will be on January 23, 2025.
14. ADJOURNMENT
The meeting adjourned at 4:17 PM.