USACE April 2021 Update
USACE April 2021 Monthly Update 1. Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Work resumed in late-February. Construction is 48% complete with a required completion date…
Metro Flood Diversion Authority
USACE April 2021 Monthly Update 1. Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Work resumed in late-February. Construction is 48% complete with a required completion date…
USACE February 2020 Monthly Update 1. Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Winter shutdown began on 18 December; work is anticipated to resume late-February. Construction…
USACE February 2020 Monthly Update 1. Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Winter shutdown began on 18 December; work is anticipated to resume late-February. Construction…
USACE October 2020 Monthly Update 1. Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Winter shutdown began on 18 December; work could resume mid-February. Construction is 46%…
USACE October 2020 Monthly Update 1 Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Placement of right dam walls and H-pile driving in stilling basin continues. Construction…
USACE October 2020 Monthly Update November 19, 2020 1 Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. The concrete approach and structure slabs downstream stepped slabs are…
USACE October 2020 Monthly Update October 22, 2020 1 Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. The concrete approach and structure slabs are complete; placement of…
The following is a press release from the office of Sen. John Hoeven HOEVEN REVIEWS RED RIVER VALLEY INLET CONSTRUCTION, OUTLINES EFFORTS TO ADVANCE FLOOD PROTECTION FOR THE REGION Senator…
USACE July 2020 Monthly Update July 23, 2020 1 Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. The current construction completion date is 7 June 2023. Anticipated…
The Diversion Board of Authority took action today to preserve its rights for further permit consideration by requesting a formal contested case hearing. This formal process will allow additional time…