The Diversion Board of Authority unanimously voted to distribute a Request for Proposals (RFP) to four companies interested in building the Diversion Channel portion of the FM Area Diversion Project.
The RFP document includes a specific outline of services a contractor would be required to complete as part of the Public-Private Partnership (P3) agreement. The four companies that received the RFP previously submitted their qualifications to the Diversion Board and were short listed last month. Responses to the RFP must be submitted to the Board in the Fall of 2017.
“This is a huge milestone for the project,” Diversion Board Chair Darrel Vanyo said. “We have a long way to go on the project, but this is one of the first steps we need to get started with construction.”
The four firms that will receive the RFP include:
- Lake Agassiz Partners (Meridiam/Walsh/AECOM)
- Red River Valley Partners (Fluor/Plenary/Ames/Barnard)
- Red River Valley Alliance (Acciona/InfraRed/North American Enterprises/Shikun&Binui)
- Red River Partners (Graham/Parsons/Alberici/BBGI)
The Southern Embankment portion of the FM Area Diversion Project is being constructed by the U.S. Army Corps of Engineers. A construction contract was awarded in November for the inlet structure that serves as the entrance to the Diversion Channel. A groundbreaking is being planned for the spring of 2017.
Read more about the RFP, Public-Private Partnerships, or the FM Area Diversion Project.
Similar Posts:
- USACE FY 2020 Work Plan Provides $100 Million for Project — February 10, 2020
- Construction Update – Diversion Inlet & Control Structure and Wild Rice River Control Structure — May 27, 2020
- Interstate 29 Road Raise Project Ready for Construction — November 3, 2020 https://fmdiversion.gov/wp-content/uploads/2020/10/I-29-Project-Map.png
- BRRWD grants permit for FM Area Diversion Project — November 6, 2020