Construction and Bidding News

Invitation to Bid – Property Structure Mitigation – Phase 50F (WP-50F)

Invitation to Bid – Property Structure Mitigation – Phase 50F (WP-50F)

INVITATION TO BID Sealed Bids for the construction of the Property Structure Mitigation – Phase 50F (WP-50F) project will be
Fargo-Moorhead Diversion Project Construction Picks Up Pace

Fargo-Moorhead Diversion Project Construction Picks Up Pace

After more than a decade of planning and legal challenges, the pace of construction on the $3 billion Red River
USACE April 2021 Update

USACE April 2021 Update

1. Diversion Inlet Structure Construction  Structure includes 3-50 ft. wide Tainter gates. Work resumed in late-February. Construction is 48% complete
Corps awards a $67 million contract for the Fargo-Moorhead diversion project

Corps awards a $67 million contract for the Fargo-Moorhead diversion project

The following is a release from the U.S. Army Corps of Engineers St. Paul District U.S. ARMY CORPS OF ENGINEERS,

Interactive Project Web Map

Animated Flyover