Construction on Work Package 43A of the Oxbow-Hickson-Bakke (OHB) Levee project, which will protect these communities from water that would be stored upstream of Fargo-Moorhead by the Diversion Project, has been completed. Design is continuing on remaining sections of the Levee.
The status of the OHB Levee project is as follows:
- WP-43A (Levee) – Completed levee construction
- WP-43C (Levee) – Completed 65% submittal and continued design work
- WP-43D (Pump station, road raises, internal drainage) – 65% submittal scheduled for end of October
- WP-43D.3.A (Gatewell prefab vertical drainage -“Preload”) – Construction started
- WP-43E.2.A (Demo) – Completed demolition of 333 Schnell Drive
Work on levees within Fargo is also progressing. Here is a list of various projects underway, and project statuses:
- WP-42H (El Zagal) – Started construction
- WP-42A.2 (2th St. N PS) – Awarded construction contract
- Industrial Builders, Inc. (IBI): $8,069,000
- WP-42A.1 & A.3 (4th St. PS and 2nd St. So. Floodwall) – Bid opening scheduled October 21, 2014
- WP-42F.1/F.2 (Floodwall and Utilities) – Continued design and coordination with New City Hall project
Similar Posts:
- Sen. John Hoeven Reviews Inlet Construction — August 25, 2020
- USACE FY 2020 Work Plan Provides $100 Million for Project — February 10, 2020
- Interstate 29 Road Raise Project Ready for Construction — November 3, 2020 https://fmdiversion.gov/wp-content/uploads/2020/10/I-29-Project-Map.png
- Construction Update – Diversion Inlet & Control Structure and Wild Rice River Control Structure — May 27, 2020