Property Acquisition Schedule
Diversion Channel Acquisition Schedule
Based on P3 procurement schedule from Sept. 2020
-
Parcels with structures: September 1, 2020
-
Land parcels (no structures): October 15, 2020
Southern Embankment Acquisition Schedule
Based on USACE schedule from July 2020
-
I-29 Road Raise:
- November 2020
-
Red River Control Structure:
- OINs 9348 & 9400: November 2020
- Remaining parcels: August 2021
-
Southern Embankment Reach 1:
November 2020
-
Southern Embankment Reaches 2-5:
General schedule shows the following dates
- Reach 2A: August 2021
- Reach 2B: August 2022
- Reach 3: July 2024
- Reach 4: July 2023
- Reach 5: July 2024
-
Drain 27 Wetland Restoration
-
July 2021
-
Upstream Mitigation Area
-
- Minnesota: January 2025
- North Dakota: January 2025
Contact Information
Cass County Joint Water Resource District (CCJWRD)
- Carol Harbeke Lewis
- Secretary-Treasurer
- 701-298-2381
AE2S, Lands Program Manager
- 701-364-9111
Moorhead Clay County Joint Powers Authority (MCCJPA)
- Steve Larson, Secretary
- 218-299-5002