Property Acquisition Schedule

Diversion Channel Acquisition Schedule

Based on P3 procurement schedule from Sept. 2020

  • Parcels with structures:  September 1, 2020

  • Land parcels (no structures):  October 15, 2020

Diversion Channel Parcels

Southern Embankment Acquisition Schedule

Based on USACE schedule from July 2020

  • I-29 Road Raise:

    • November 2020
  • Red River Control Structure:

    • OINs 9348 & 9400:  November 2020
    • Remaining parcels:  August 2021
  • Southern Embankment Reach 1:

    November 2020

  • Southern Embankment Reaches 2-5:

    General schedule shows the following dates

    • Reach 2A:  August 2021
    • Reach 2B:  August 2022
    • Reach 3: July 2024
    • Reach 4: July 2023
    • Reach 5: July 2024
  • Drain 27 Wetland Restoration

    • July 2021

Southern Embankment Parcels

Upstream Mitigation Area

    • Minnesota: January 2025
    • North Dakota: January 2025

Upstream Mitigation Area Parcels

Contact Information

Cass County Joint Water Resource District (CCJWRD)

  • Carol Harbeke Lewis
  • Secretary-Treasurer
  • 701-298-2381

AE2S, Lands Program Manager

  • 701-364-9111

Moorhead Clay County Joint Powers Authority (MCCJPA)

  • Steve Larson, Secretary
  • 218-299-5002