Settlement Terms Sheet
See the signed copy of the Binding Settlement Term Sheet Execution Copy BINDING SETTLEMENT TERM SHEET By and Between METRO FLOOD DIVERSION AUTHORITY and RICHLAND-WILKIN JOINT POWERS AUTHORITY and BUFFALO-RED…
See the signed copy of the Binding Settlement Term Sheet Execution Copy BINDING SETTLEMENT TERM SHEET By and Between METRO FLOOD DIVERSION AUTHORITY and RICHLAND-WILKIN JOINT POWERS AUTHORITY and BUFFALO-RED…
The Metro Flood Diversion Authority announced today that it has received approval of the Property Rights & Acquisition Mitigation Plan (Mitigation Plan) for the Fargo Moorhead Area Diversion Project from…
The FM Area Diversion Project requires different types of property rights to build and operate the Project. The Project requires the acquisition of over 9,000 acres for the construction footprint…
Moorhead, Clay County form Joint Powers Authority to Support Implementation of the FM Area Diversion Project (Aug. 15, 2019) The City of Moorhead and Clay County, MN have formed a…
With the recent warning from the National Weather Service of increased flooding this spring, it is a good time to reflect that this year marks 10-years since the record-setting 2009…
The first of a two phase study was recently completed by Crown Appraisals, Inc. for the FM Area Diversion Project. Fully understanding impacts of the Project has been a top…
Diversion Channel Acquisition Schedule Based on P3 procurement schedule from Sept. 2020 Parcels with structures: September 1, 2020 Land parcels (no structures): October 15, 2020 Southern Embankment Acquisition Schedule Based…
Land Acquisition Land Management Plan Doc Date: July 12, 2012 Editor’s notes: Land Management Plan provides an overview of the land management and acquisition requirements for the construction for the…
Pre-PPA hardship policy Doc date: April 12, 2012 Editor’s notes: Hardship policy establishes the policy for early buyout of residential property where it is determined that a property owner suffers…