USACE March 2021 Update
USACE February 2020 Monthly Update 1. Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Winter shutdown began on 18 December; work is anticipated to resume late-February. Construction…
USACE February 2020 Monthly Update 1. Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Winter shutdown began on 18 December; work is anticipated to resume late-February. Construction…
USACE February 2020 Monthly Update 1. Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Winter shutdown began on 18 December; work is anticipated to resume late-February. Construction…
USACE October 2020 Monthly Update 1. Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Winter shutdown began on 18 December; work could resume mid-February. Construction is 46%…
USACE October 2020 Monthly Update 1 Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. Placement of right dam walls and H-pile driving in stilling basin continues. Construction…
USACE October 2020 Monthly Update November 19, 2020 1 Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. The concrete approach and structure slabs downstream stepped slabs are…
USACE October 2020 Monthly Update October 22, 2020 1 Diversion Inlet Structure Construction Structure includes 3-50 ft. wide Tainter gates. The concrete approach and structure slabs are complete; placement of…